The Federal Government has cancelled $717.7m in undisbursed World Bank financing for Nigeria’s troubled electricity sector, effectively terminating the remaining portion of a $1.52bn power sector recovery programme amid mounting tariff shortfalls, worsening financial pressures, and persistent implementation challenges across the industry.
- +FG cancels $717m W’Bank power loan amid blackouts
Documents obtained by The PUNCH from the World Bank website on Monday showed that the cancellation followed a formal request by the Federal Government and a joint decision by both parties to discontinue financing under the Power Sector Recovery Performance-Based Operation due to evolving sector realities and the inability to achieve key reform milestones.
Documents obtained by The PUNCH from the World Bank website on Monday showed that the cancellation followed a formal request by the Federal Government and a joint decision by both parties to discontinue financing under the Power Sector Recovery Performance-Based Operation due to evolving sector realities and the inability to achieve key reform milestones.
According to the World Bank restructuring paper, the cancelled amount represents the entire undisbursed balance remaining under the programme. “The restructuring will result in the cancellation of the entire undisbursed balance in the amount of $717.7m equivalent, and no further disbursements will be made under the Program following approval of this restructuring,” the bank stated.
The bank also disclosed that the programme’s closing date had been brought forward from June 30, 2027, to May 31, 2026, effectively ending the operation more than a year ahead of schedule. The cancelled facility formed part of a broader World Bank intervention designed to revive Nigeria’s struggling power sector.
The original Power Sector Recovery Performance-Based Operation was approved on June 23, 2020, with financing of about $752.5m equivalent. The programme was structured to improve electricity supply reliability, strengthen the sector’s financial and fiscal sustainability, and enhance accountability among key institutions in the electricity value chain.
Following initial progress recorded under the programme, the World Bank approved an Additional Financing package of approximately $763.5m equivalent on June 9, 2023, to consolidate earlier gains and support a new phase of reforms. The financing became effective on June 19, 2024, and extended the project’s closing date to June 30, 2027.
Together, the original financing and the additional facility amounted to about $1.52bn.
However, while the parent programme achieved substantial results and largely disbursed its resources, the additional financing struggled to meet critical reform conditions, resulting in limited disbursements and eventual cancellation of the remaining funds.
The World Bank noted that Nigeria’s electricity sector continues to face deep-rooted structural challenges despite years of reforms and significant financial support.
The report stated that the sector still suffers from weak distribution performance, transmission bottlenecks, underutilisation of available generation capacity, and persistent financial imbalances.
According to the bank, high technical, commercial, and collection losses across the distribution segment, combined with inadequate cost recovery, have created a recurring mismatch between revenues generated by the sector and its actual operating costs.
“These constraints have created recurrent financing gaps, most notably in the form of tariff shortfalls, which generate liquidity pressures across the value chain and weaken the operational and financial performance of sector institutions,” the report said.
The Federal Government developed the Power Sector Recovery Programme as a framework to restore the sector’s financial viability and reduce its fiscal burden on public finances.
The programme included plans to progressively eliminate tariff shortfalls, improve operational performance among power sector institutions, and strengthen regulatory oversight and accountability mechanisms.
According to the World Bank, implementation of the original operation delivered notable results. The report stated that tariff shortfalls fell by 71 per cent between 2019 and 2022, declining from N581bn to N166bn.
During the same period, regulatory cost recovery improved significantly from 56 per cent to 94 per cent, while annual electricity supplied to the distribution grid increased by 13 per cent between 2018 and 2021.
The bank said all standard disbursement-linked indicators and global indicators attached to the original programme were fully achieved. “Implementation of the parent operation was satisfactory, brought substantial results, and fully disbursed the PforR component as all DLRs were achieved,” the report stated.
Encouraged by those gains, the World Bank approved the additional financing package to address remaining structural weaknesses and deepen reforms under the Power Sector Recovery Programme.
The new facility was expected to support the development of a sustainable financing framework for the sector, improve operational performance through implementation of performance improvement plans, and strengthen governance arrangements among electricity institutions, particularly the Transmission Company of Nigeria.
However, the anticipated reforms failed to materialise within the expected timeframe. The World Bank attributed much of the setback to major macroeconomic developments that dramatically altered the operating environment.
According to the report, the liberalisation of Nigeria’s foreign exchange market in June 2023 triggered a sharp depreciation of the naira, leading to a substantial increase in the cost of natural gas used for electricity generation.
The bank explained that more than 70 per cent of electricity supplied into Nigeria’s national grid is generated using natural gas, whose pricing is denominated in United States dollars.
“The liberalisation of the foreign exchange market in June 2023 led to a significant depreciation of the local currency Naira, which resulted in a big increase in prices of natural gas used to produce above 70 per cent of electricity injected in the national power system,” the report stated.
At the same time, electricity tariffs for most consumers remained largely unchanged despite rising generation costs. The World Bank noted that electricity tariffs had effectively been frozen since early 2023, except for Band A customers, whose tariffs were adjusted to cost-reflective levels in April 2024.
This widening gap between actual electricity production costs and revenues collected from consumers resulted in a sharp increase in tariff shortfalls. According to the report, annual tariff shortfalls rose from a low of N140bn in 2022 to approximately N1.9tn in both 2024 and 2025.
“Due to the mismatch between the electricity generation costs and the sector tariff revenues, the tariff shortfalls increased sharply in the last 3 years, moving from a low of N140bn in 2022 to a high of N1.9tn per year in 2024 and 2025, putting serious pressure on the limited Federal Government of Nigeria’s fiscal space,” the World Bank said.